Southern California Edison's published interconnection queue shows a current average st…

Southern California Edison's published interconnection queue shows a current average study-to-energization timeline of approximately 3.5 years for comparable industrial loads in the region.

Verified
Original Observation

No upstream observation on record — this evidence predates the Observation Bus, or was entered directly by an analyst.

Extracted Claim

Southern California Edison's published interconnection queue shows a current average study-to-energization timeline of approximately 3.5 years for comparable industrial loads in the region.

Supporting Sources
Regional infrastructure data
infrastructuresiting
Confidence
HighReviewed by Project Lead · Accepted 2026-05-01
Linked Entities
Linked Risks

No probabilistic risks linked.

Linked Constraints

No structural constraints linked.

Affected Scenarios

No scenarios reference this evidence.

Affected Decisions

No decisions cite this evidence.

Related Evidence
IDNotesConfidence
EV-061Interconnection cost estimates from SCE's publicly available fee schedule suggest $12–18 million in network upgrade costs could be allocated to this project depending on final queue position.High
Timeline
2026-05-01Evidence Added

Evidence Imported

Southern California Edison Interconnection has documented infrastructure capacity relevant to program logistic

by Research Analyst

Replay References

This evidence is not cited in any decision replay yet.