Heilongjiang Spheronization Facility
Secondary spheronization facility referenced for capacity benchmarking.
Spheronization FacilityExisting
Summary
Evidence
Open evidence ledger →| ID | Date | Category | Source | Confidence | Status | Notes |
|---|---|---|---|---|---|---|
| EV-038 | 2026-04-01 | Technical | Technical literature | Medium | Under Review | Heilongjiang facility is the northernmost option under evaluation and carries the longest inland transport distance to coastal export ports among the three non-domestic alternatives. |
| EV-039 | 2026-04-02 | Technical | Technical literature | Medium | Verified | Regional power costs in Heilongjiang are reported as among the lowest of the three spheronization alternatives, partially offsetting the longer logistics chain. |
Relationships
| From | Relation | To |
|---|---|---|
| Spheronization Facility (non-domestic) | Alternative to | Heilongjiang Spheronization Facility |
Risks
Open risk register →Land parcel title risk (Parcel A)
An initial title review question on Parcel A has been resolved with no outstanding issues.
LowResolved
Land parcel rail access risk (Parcel B)
Parcel B is farther from existing rail access, which would require additional inland transport infrastructure.
MediumOpen
Scenarios
Open scenario workspace →This entity is not a dependency of any scenario yet.
Open Decisions
Open decision queue →Confirm Parcel A as preferred site
Confirm Parcel A as the preferred processing-site location following resolved title review.
MediumApproved
Hold Parcel B as backup site
Retain Parcel B as a backup site pending rail access resolution.
LowReview
Timeline
2026-04-02Evidence Added
Evidence Imported
Heilongjiang Spheronization Facility throughput and yield figures have been benchmarked against comparable fac
by Research Analyst