Atlas
Project 001 · Understand How This Decision Was Made

Qualify second spheronization facility

Begin qualification of a second non-domestic spheronization facility to reduce single-facility dependency.

Review
Everything below reflects exactly what was known as of 2026-06-09 — the evidence available, the risks on record, and the reasoning that followed. Nothing here has been revised with hindsight.
Decision Rationale
High

No rationale recorded for this decision.

Supporting Evidence Cited
IDDateCategoryConfidenceNotes
EV-0242026-03-12InfrastructureHighSite diligence identifies an existing Class II hazardous waste permit held by the prior tenant, which could shorten the DTSC re-permitting timeline by an estimated 6–9 months versus a greenfield site.
EV-0252026-03-13InfrastructureHighGulf Coast site benefits from existing rail and barge access but sits within a NOAA-designated Category 3 hurricane storm surge zone, requiring elevated pad construction.
Evidence Available Then
88 records existed as of 2026-06-09
IDDateCategoryNotes
EV-0872026-06-09Supply ChainCalcined petroleum coke suitable for synthetic graphite production is available from at least three Gulf Coast refiners, reducing single-supplier exposure relative to the sulfuric acid position.
EV-0862026-06-08Supply ChainPetroleum coke feedstock pricing has moved within a $310–380 per tonne range over the trailing twelve months per commodity market data, a wider band than assumed in initial program cost estimates.
EV-0852026-06-05Supply ChainQuoted delivered pricing from the engaged supplier is approximately $145–160 per tonne, consistent with regional industrial acid market data from early 2026.
EV-0842026-06-04Supply ChainOnly one sulfuric acid supplier has been engaged in preliminary discussions; two additional regional suppliers were contacted but have not responded as of this evidence date.
EV-0832026-06-03MarketIntegrator has indicated openness to a shorter qualification cycle than cell manufacturers, given less stringent cycle-life requirements for stationary storage applications.
EV-0822026-06-02MarketGrid Storage Integrator West's projected annual material demand, per its public capacity expansion announcements, is estimated at 8,000–12,000 tonnes by 2028 — meaningful but secondary to primary battery-cell offtake volume.
EV-0812026-06-01MarketConsortium's technical qualification standard (per published supplier requirements) is broadly similar to Cell Maker A's protocol but includes an additional carbon-footprint disclosure requirement.
EV-0802026-05-29MarketEuropean Battery Consortium's public sourcing roadmap targets 30% non-Asian anode material supply by 2030, a stated policy goal consistent with program positioning but not yet a signed commitment.
EV-0792026-05-28EnvironmentalNo federally listed endangered species habitat has been identified within the immediate project footprint per the most recent U.S. Fish and Wildlife Service critical habitat mapping.
EV-0782026-05-27EnvironmentalColorado River Delta habitat review precedent from a comparable cross-border infrastructure project suggests binational environmental consultation could add 6–12 months to permitting if triggered.
EV-0772026-05-26EnvironmentalComparable processing facilities elsewhere have achieved PM10 compliance using baghouse filtration systems with a documented capture efficiency above 99.5%.
EV-0762026-05-25EnvironmentalSalton Sea Air Basin is currently classified as nonattainment for PM10 under federal standards, which imposes additional emissions offset requirements on new industrial sources.
EV-0752026-05-22PermittingA preliminary wetlands delineation survey commissioned for this program identified no jurisdictional wetlands within the primary site boundary, though the adjacent water infrastructure corridor remains under review.
EV-0742026-05-21PermittingArmy Corps jurisdictional determination requests for comparable water-adjacent industrial sites in the region have taken a median of 14 months to resolve per publicly available Corps case data.
EV-0732026-05-20PermittingCounty planning staff confirmed in a pre-application meeting that no general plan amendment would be required for the current site configuration, reducing procedural risk.

Showing 15 of 88 records available at replay time.

Risks Known Then
44 risks logged as of 2026-06-09
Madagascar jurisdictional policy risk

Madagascar's export policy for graphite has been broadly stable but is not contractually locked in.

LowMonitoring
Mozambique jurisdictional policy risk

Mozambique's regulatory and export policy environment for critical minerals is still developing.

MediumOpen
Production tax credit policy risk

The critical minerals production tax credit is subject to future policy change.

MediumMonitoring
Offtake prepayment structuring risk

Prepayment facility terms are still under negotiation and could affect capital structure assumptions.

LowMonitoring
Federal loan guarantee approval uncertainty

Department of Energy loan guarantee approval timing and terms remain uncertain.

MediumOpen
Synthetic feedstock cost volatility

Petroleum coke feedstock pricing for the synthetic hedge pathway has shown recent volatility.

LowMonitoring
Process chemical supplier concentration risk

Sulfuric acid supply for purification currently depends on a single candidate supplier.

MediumOpen
Grid storage customer volume uncertainty

Grid storage integrator demand volume is less certain than primary battery-cell offtake.

LowMonitoring
Unknown Factors

No unknown factors recorded for this decision.

Outcome

Outcome not yet recorded — this decision may still be open.

Lessons Learned

No lessons learned recorded for this decision.